DRDT-2 Setup

  • Allan Allan
  • August 18, 2020August 20, 2020
  • Workshop, Tools
  • Hours logged: 2

Assembled the DRDT-2 deep reach dimpling tool and built side support platforms for the skins. I didn’t follow the provided plan and instead created two separate platforms. That will let me move them around as needed for larger skins and make it easier to store them.

previousGear Down
nextEmpennage Kit Inventory
Category Hrs Progress
Workshop 21.5 100%
Setup 16 100%
Tools 5.5 100%
Empennage 294.7/296 100%
Inventory 2 100%
Vertical Stabilizer 16 100%
Rudder 27.6 100%
Horizontal Stabilizer 47.5 100%
Elevators 65.4 100%
Tail Cone 88.3 100%
Attach 21.9 100%
Fairings 26/27 96%
Fuselage 484.2/488 99%
Inventory 4.5 100%
Mid Fuse 64.3 100%
Firewall 24 100%
Fwd Fuse 40 100%
Side Skins 74.3 100%
Steps 4.2 100%
Upper Fwd Assembly 12 100%
Tail Attach 9 100%
Baggage Area 29.5 100%
Baggage Door 13 100%
Covers & Floor Panels 28 100%
Brake Lines 10 100%
Fuel System 9 100%
Rudder Pedals 1 100%
Control System 15.2 100%
Flap System 3.8 100%
Upper Fwd Install 13 100%
Rear Seat Backs 7 100%
Cabin Top 122.4/126 97%
Wings 60/75 80%
Fuel Tanks 14 100%
Bottom Wing Skins 21/25 84%
Aileron Actuation 17/18 96%
Wing Tips 0/10 0%
Pitot/AoA 8 100%
Finish Kit 282/414 68%
Engine Mount 3 100%
Landing Gear 4/10 40%
Spinner and Cowling 0/80 0%
Gear Leg and Wheel Fairings 0/40 0%
Seats and Seat Belts 8/14 57%
Inventory 2 100%
Doors & Transparencies 265 100%
Firewall Forward 31/165 19%
Oil Cooler 27/27 99%
Mount Engine 0/10 0%
Cowl Baffle 0/40 0%
Control Cables 4/8 50%
Fuel System 0/20 0%
Oil System 0/10 0%
Exhaust System 0/20 0%
Sensors/Instrumentation 0/20 0%
Preheater 0/10 0%
Avionics/Wiring 187.9/350 54%
Other 135.8/152 89%
Interior 62/64 96%
Engine Build 20 100%
Oxygen 8/20 40%
A/C 45.8/48 96%
Total 1497.1/1961 76%

I have averaged 5.53 hrs/week (0.79 hrs/day) and have about 464 hours remaining.

Some guesses as to how long it might take to finish:
• At my average rate (May 2027)
• At 8 hrs/week (November 2026)
• At 12 hrs/week (July 2026)
• At 14 hrs/week (May 2026)